| Demolition
of Old Nashville Thermal Waste-to-Energy Plant Completed
Overall Cost of Demolition Reduced
by Used Equipment Auction Netting Metro Over $983,000
Fairfax, Virginia (January 11, 2005)
- The 9-acre site of the former Nashville Thermal Transfer
Corporation facility, situated along the downtown riverfront,
is now available for new development after a successful innovative
cost-effective demolition process managed by Gershman, Brickner
& Bratton, Inc. (GBB) of Fairfax, Virginia. The Thermal
facility, which served as a waste-to-energy plant from 1974
through the Spring of 2002, has been replaced by a new fossil-fuel
fired district energy generating plant (www.nashville.gov/des/),
while the solid waste remaining after Metro Nashville’s
new recycling programs is now transferred to out-of-County
landfills.
One of the unique aspects
of the “dismantling of Thermal” was an auction
process of Thermal’s fixed and mobile equipment and
parts stockpile. Over 150 auction transactions for the resale
and reuse of used equipment brought over $983,000 to the Metro
Nashville government, owner of the Thermal assets, reducing
the overall net cost to demolish Thermal.
In GBB’s initial planning
of December 2000, it was estimated that the total demolition
cost would be $2.5 million, exclusive of contingencies and
consultant costs. However, as of December 2004 and accounting
for the five different contractor’s that were ultimately
selected to be involved in the total process, the overall
gross costs for dismantling the entire facility was approximately
$1.1 million producing a total net cost of only $120,000
after accounting for the $983,000 proceeds from auctioning
off equipment.
“Metro Nashville decided
to approach the demolition project as an opportunity, not
a means to an end,” noted GBB’s Senior Vice President
Robert Brickner, “An opportunity to save money through
the well-thought out integration of reuse, recycling and organized
demolition techniques coordinated through demolition services
procured through GBB, an experienced consulting firm familiar
with the demolition industry. Too many cities have their local
architects and engineering firms, who are experts in designing
new buildings, also act as their demolition consultants. Nashville
recognized that their project was not a cookie-cutter one,
reached out for construction & demolition waste (C&D)
expertise that sees the big picture, and Metro reaped the
financial benefits.”
The entire project included
the use of five different contractors managed by GBB. After
the auction events, and contracting separately for asbestos
abatement and underground storage tank removal, on April 19,
2004, the Nashville Thermal Transfer Corporation formally
turned over what remained of the 30-year-old Thermal Waste-to-Energy
plant to Anderson Excavating Company of Omaha, Nebraska, for
complete dismantlement. The Anderson work included the late-July
implosion of the large 200 feet concrete two-flue stack.
Considering all site-related
work, GBB has calculated that 98.5%, by weight, of all the
materials within the old waste-to-energy plant site were either
salvaged for reuse, or processed for recycling including materials
such as crushed concrete aggregate, crushed asphalt, metals,
railroad ties and used equipment. New Metro Nashville public
works construction projects were the strategic recipients
of many of these recycled materials, saving the costs of buying
virgin materials.
GBB is a national solid
waste management consulting firm founded in 1980 that works
on solid waste collection, processing, recycling and disposal
issues, including construction waste and demolition debris
projects at the local, state, and national levels for both
the public and private sectors. GBB is a national leader in
providing C&D waste management consulting, assisting clients
in developing sound and cost-effective approaches to improve
the handling, processing, recycling, and/or disposal of C&D
waste materials. For more information on the firm and its
products and services, visit www.gbbinc.com
or call 1-800-573-5801.
|